Various air conditioners Ventilation pipe construction And installation
The thickness of galvanized steel plate shall be selected in the processing workshop according to the list of materials used for the fabricated air duct, the galvanized steel plate shall be loaded into the leveling and reinforcing machine from the loading frame, and the machine shall be started to cut off the end of the steel plate. When loading, check whether the steel plate is inclined, try to cut a steel plate, and measure whether the cut line of the sheared steel plate is vertical to the edge line, and whether the diagonal line is consistent.
Input the cutting length and quantity in the material list into the computer, start the machine, and the computer will automatically cut and press the reinforcement. The sheet cutting must be rechecked to avoid mistakes.
ACL3100 plasma cutting machine is used for special shaped plates, and on-site electric shears are used for cutting sporadic materials. When using fixed dynamic shears, two hands should hold the steel plate, and the distance between the hands and the knife edge should not be less than 5cm. The force should be uniform and appropriate.
Ventilation duct Detailed rules for construction, installation and fabrication specifications
Ventilation engineering In, the production and installation of ventilation ducts are important links. What specific requirements and specifications are there in the production and installation methods? This is the content that all individuals or enterprises who process ventilation ducts and undertake ventilation projects should study. The following requirements and specifications are essential in the production and installation of ventilation ducts!
1. The main materials, equipment, finished products and semi-finished products used in ventilation and air conditioning works shall be provided with factory certificates or quality appraisal documents.
2. The tee of circular air duct has an included angle of 90 º.
3. Ventilation works must be constructed according to the approved design drawings.
4. The size of the ventilation pipe shall be constructed according to the drawing, and the inner diameter shall prevail. The connecting pipe shall be consistent with the valve body.
5. The connection of each section of air duct shall be detachable.
6. The bending radius and the number of small sections of circular bends and the bending radius of rectangular bends shall be in accordance with the relevant provisions of the Technical Operation Specification for Construction of Building and Installation Engineering.
7. The thickness of air duct shall comply with the standard.