You know? Ventilation duct works How should the construction be arranged?
The air duct that discharges moist gas or contains water vapor shall have a slope of not less than 0.005, and drainage measures shall be taken at the low point of the air duct and the bottom of the fan.
Corresponding anti-corrosion measures shall be taken for ventilation equipment, air ducts and accessories according to the environment and corrosiveness of the gas, steam or dust transported.
Ventilation pipe construction Installation requirements:
1、 Material requirements
1. All kinds of plates and pipes shall be provided with quality certificates (including factory certificates, quality certificates and test reports) and product lists. Ventilation engineering Construction and installation requirements
2. The finished air duct shall be free from deformation, distortion, cracking, holes, flange falling off, open welding, missing riveting, missing bolt holes and other defects.
3. The installed valve body silencer, cover, air outlet and other components shall be checked to see whether the regulating device is flexible and whether the silencer and paint layer are damaged.
4. Materials used for installation: suspender, bolt, nut, washer, gasket, sealing strip, self tapping screw, rivet, canvas, non-woven fabric, expansion bolt, etc. shall meet the product quality requirements.
2、 Installation requirements
1. Locate the suspender laying position according to the center line of the air duct. Single suspender is on the center line of the air duct, and double suspenders can be installed symmetrically according to the screw hole spacing of the tray or the center line of the air duct.
2. The suspender can be welded or hung on the suspender according to the form of the suspender. After welding, it should be coated with anti rust paint.
When a row of supports is required to be installed for a long air duct, the two ends can be installed first, and then the elevation of the middle support can be found out by the guy method based on the supports at both ends.
3. When installing the riser pipe clamp, first fix one of the pipe fittings above, then hang the line at the center with a plumber, and then fix the pipe clamp below according to the line.
4. If there is no design requirement for the spacing of air duct supports and hangers, the uninsulated air duct shall meet the requirements in the following table. If there is no design requirement for the spacing between supports and hangers of insulated air ducts, the required spacing value in the following table shall be multiplied by 0.85. Spiral duct The spacing between supports and hangers can be increased appropriately.