fire control Construction of smoke exhaust works Installation of middle smoke exhaust pipe and accessories
1、 Ventilation engineering The smoke exhaust pipe for construction should be steel pipe or cast iron pipe. When welded steel pipes are used, their wall thickness shall be greater than 3mm; The pipe connection should be welded. When flange connection is adopted, the flange surface shall be flat and there shall be sealing groove; Heat resistant rubber gasket shall be padded between flanges.
2. Cast iron smoke exhaust pipe buried in concrete should be connected by flange.
3. The smoke exhaust pipe shall be equipped with thermal expansion compensator along the axis direction. The one-way casing expansion joint shall be concentric with the front and rear smoke exhaust pipes. The connecting section between the diesel engine exhaust pipe and the main exhaust pipe shall be equipped with buffer facilities.
4. The installation of smoke exhaust pipe shall meet the following requirements:
(1) The gradient should be 0.5% larger, and the drain valve should be set at a lower place;
(2) The cleaning hole blocking plate shall have a heat-resistant cushion and be firmly fixed;
(3) When the smoke exhaust pipe passes through the partition wall, the surrounding space shall be filled with asbestos rope;
(4) At the connection between the smoke exhaust pipe and the smoke exhaust duct, the sealed through wall short pipe with flange and sealed wing ring shall be embedded.
(5) The ground outlet end of the smoke exhaust pipe shall be equipped with a rain cap; Measures shall be taken to prevent smoke exhaust pipe from blocking at 150~200mm above the ground.
The article comes from the network, if you have any questions, please contact us!